Menu

Far More is Happening Here

Flooding Hero Image

Oakcreek Area Flood Risk Management

This project was bid on June 3, 2015 and H&S Contracting was chosen as the contractor. The project started on 25th Street and involved the construction of an earthen levee over vacated lots. A project overview map is located on the right hand side of this page.

Construction Timeline

Levee construction was completed in 2015 while landscaping was completed in 2016. Final project acceptance is expected in 2017.


July 24, 2018 Update

An additional phase of the Oakcreek and Copperfield Court project is awaiting the purchase of two remaining homes in order to complete a continuous line of protection from 40th Avenue South to 25th Street South. In this final phase, a new storm sewer lift station and associated piping will be installed along with several hundred feet of earthen levee. The buyouts are anticipated to be completed in 2018 with the final phase of construction commencing in 2019.