This is an overview of the commercial building plans and permitting process. Overall time required depends on the quality of plans and the number of resubmittals required prior to approval. Reviews for specific items are conducted by the Inspections, Planning and Development, Engineering, Fire and Fargo Cass Public Health departments.

View the "More Information" section to the right or continue scrolling if on a mobile device for more detailed descriptions of each department’s review portfolio.


Step 1

Pre-Application Meeting

A voluntary information meeting to discuss conceptual designs. Call the Planning and Development Department at 701.241.1474 to set up a meeting. Some designs may also require a Public Hearing; this can be determined during this step.

View the Step 1 Process

Step 2

New Project Submittal

Plans are submitted to the Inspections Department. Inspections then routes plans to the Engineering, Planning and Development, Fire and Fargo Cass Public Health departments for review.

View the Step 2 Process

Step 3

Technical Reviews

Each receiving department reviews specific items in the submittal. Review comments are compiled and returned to the designer/owner.

View the Step 3 Process

Step 4

Review Response

The applicant's team modifies the design to address the comments received from City staff members. The revisions are resubmitted through the Inspections Department.

View the Step 4 Process

Step 5

Resubmittal Review

Staff will review the applicant's resubmittal and comment again or approve the plan. If there are additional comments, the plan returns to Step 2.