Seal Coat Project: 2023
Zone: North, SouthWhat zone am I?
Completed
Start: June 2023
Estimated Completion: End of July 2023
Current Status (Updated 11/17/2023):
This project is now complete.
Overall Map
Project Overview:
This project is part of the City's annual infrastructure improvement efforts and impacts multiple areas of Fargo each construction season. Seal coat projects extend the life of asphalt pavement and provide a more traffic and weather resistant surface. It involves spraying an asphalt emulsion on the pavement surface, immediately followed by a rock chip application that is embedded into the emulsion. The 2023 project will take place in multiple locations throughout the City.
Impacts:
Traffic will be maintained during construction, but short-term lane closures and parking restrictions are required to safely accommodate construction activity.
Construction activity will be performed in multiples areas of the City. To view the affected areas, please refer to the Overall Project Map via the Project Resources section on the right side of this page.
Contractor:
Asphalt Preservation Company, Inc.
Timeline:
This project is scheduled to start in June of 2023 and be completed by the end of July 2023.
Funding:
This project will be funded by Street Sales Tax Funds and Special Assessments.
Purpose:
The annual seal coat project extends the pavement life of our City streets and helps prevent future wear from weather and traffic. This preventative maintenance ultimately saves residents and the City money, time, and resources.