Menu

Far More is Happening Here

FargoStreets Hero Image

33rd Street North Construction


Zone: NorthWhat zone am I?

Completed

Start: May 7th, 2018

Estimated Completion: Fall 2018

Overall Map
Overall Map

Overall Map


Current Status:

Construction along 33rd St North began May 7th, 2018 and was completed by August 2018.


Project Overview:

This project is for the new construction of underground utilities, concrete pavement and incidentals on 33rd Street North. There will also be improvements made to 40th Avenue North near the intersection of 33rd Street North.


Impacts:

During construction 33rd Street North will be closed during the street paving operation. A detour route will be implemented during this period for all local traffic. During the work on 40th Avenue North thru traffic will be able to pass at a reduced speed.


Contractor:

Dakota Underground


Timeline:

This project started the week of Monday, May 7th, 2018 and has a Substantial Completion Date of August 1st, 2018.


Funding:

Special Assessment


Purpose:

This project will allow for continued development of the land along 33rd Street North as requested by the developer.