25th Street & 13th Avenue South Intersection Reconstruction and 25th Street South CPR Work


Zone: SouthWhat zone am I?

Completed

Start: September 2017

Estimated Completion: September 2018

Project Overview Map
Project Overview Map

North Portion CPR Project Overview Map


Current Status:

Crews have reopened all driving lanes of 25th Street South and restored access at the 5th Avenue South intersection. Motorist are again carried in two lanes plus turning lanes on an improved driving surface in both directions.

Following the completion of the repair work, crews will be doing some surface grinding to improve the ride quality and install permanent pavement markings. This work will be completed under traffic using flaggers.


Project Overview: North Portion CPR Work

In CPR projects, crews remove the bad areas of the driving surface and replace the area with new concrete. Sections of the roadway will re-open to traffic once designed strength has been achieved on the new concrete. There may be periods of time when workers are not present in the zone while concrete is curing over a period of time.

North Portion Work Zone: 25th Street South from north of 13th Avenue South to south of the railroad crossing near 2nd Avenue South.


Impacts:

North Portion CPR Work: Traffic was carried in a single lane in each direction through a two-block section at a time on 25th Street South north of 13th Avenue South to south of the railroad crossing near 2nd Avenue South.


Timeline:

The north section of the CPR project is complete. Crews will be doing some surface grinding to improve the ride quality and install permanent pavement markings. This work will be completed under traffic using flaggers.


South Portion CPR Work Traffic Pattern
South Portion CPR Work Traffic Pattern

South Portion CPR


Project Overview: South Portion of CPR Work

In CPR projects, crews remove the bad areas of the driving surface and replace the area with new concrete. Sections of the roadway will re-open to traffic once designed strength has been achieved on the new concrete. There may be periods of time when workers are not present in the zone while concrete is curing over a period of time.

The South Portion CPR Work Zone was from south of 13th Avenue South to 17th Avenue South. Work was completed on the last phase of the south section of the CPR project in mid-June.


Timeline:

Work was completed on the last phase of the south section of the CPR project in mid-June.


Project Overview: 25th Street & 13th Avenue Reconstruction

In recent years, the pavement located in the intersection of 25th Street and 13th Avenue South had been experiencing excessive deterioration and lots of potholes had developed. The pavement was beyond preventive maintenance repairs to keep the driving surface safe for motorists.

The completed project aided in extending the useful life of this pavement by replacing the deteriorated pavement and restoring its structural integrity, therefore delaying future deterioration and improving ride quality. In addition to pavement repairs, the contractor also be replaced some sections of sidewalk that had become uneven or needed to be updated to meet current standards for the Americans with Disabilities Act.


Timeline:

On Saturday, June 2 crews completed the building of the permanent center medians at the intersection of 13th Avenue and 25th Street South and removed all traffic control. For drivers, this means additional through lanes and all turn lanes will be open for use in between the repair projects on 25th Street South.