Mill & Overlay Projects: 2024
Zone: North, SouthWhat zone am I?
Current
Start: April 2024
Estimated Completion: Fall 2024
Current Status (Updated 8/27/24):
- PR-24-F1
- The Contractor is currently working on sanitary sewer pipe repairs in Area 5. This will be followed by an asphalt overlay on 1st Avenue South in the coming weeks. They also plan on milling portions of Area 3 on August 30th. They will then pave the streets in Area 3 starting on September 3rd with a road closure in place on 4th Street North from 1st Avenue North to 4th Avenue North.
- PR-24-G1
- The Contractor is planning on milling and paving streets in Area 5 starting the week of September 3rd. After completing this work they will move to Area 4 and work on milling and paving. Then they will move into Area 7 to complete an overlay. Additionally, the landscaping contractor is working on prepping areas that were damaged during curb or sidewalk replacement.
Overall Map
Project Overview:
These projects are part of the City's annual infrastructure improvement efforts and impact multiple areas of Fargo each construction season. The purpose of the projects is to correct deficiencies on the streets which have developed over time.
As part of the projects, the Contractor will be mud-jacking sections of the curb and gutter in an effort to alleviate major drainage problems. This process involves coring small holes through the curb and gutter section (and driveway apron when necessary) and injecting grout through holes to raise the gutter to the desired grade.
The Contractor will replace areas of broken up pavement as well as a limited amount of curb & gutter. The Contractor will also be replacing some sections of sidewalk that need to be updated to meet new standards for the Americans with Disabilities Act. The projects will take place in several different areas across the city.
Impacts:
Traffic will be maintained during construction, but some lanes may be closed/detoured at times or parking temporarily reduced for work being done. Sidewalks will be closed at times to allow construction to take place.
Contractors:
- PR-24-F1: Northern Improvement Co.
- PR-24-G1: Border States Paving
Timeline:
Construction will begin in April and will continue throughout the season with substantial completion scheduled for the end of September. Not all areas will have construction going on the whole time.
Funding:
This portion of the project will be funded with a combination of Sales Tax Funds and Special Assessments to the benefiting properties, with 50% being funded by Sales Tax Funds and 50% being funded by Special Assessments. Assessed costs are apportioned according to the policy established by the Fargo City Commission.
FargoParcels.com is a good resource to view the current estimated special assessments for your property. Property owners will receive an estimate for their property. The estimate will change once the project is bid and completed. Special Assessments are payable over 15 years with interest applied.
Purpose:
These projects are needed to correct deficiencies on the streets that have developed over time. Most of the roads in these areas have not had any structural work done to them for 20 years or more. By milling and overlaying the roads at this time, we can extend the life of the road and get a better riding street with improved drainage.