Menu

FargoStreets Hero Image

Mill & Overlay Projects: 2023


Zone: North, SouthWhat zone am I?

Completed

Start: May 2023

Estimated Completion: Fall 2023

Current Status (Updated 11/15/23):

  • PR-23-E1
    • This project is substantially complete.
  • PR-23-F1
    • This project is substantially complete.
  • PR-23-G1
    • This project is substantially complete.

PR-23-E1_F1_G1_OverallMap

Overall Map


Project Overview:

These projects are part of the City's annual infrastructure improvement efforts and impact multiple areas of Fargo each construction season. The purpose of the projects is to correct deficiencies on the streets which have developed over time.

As part of the projects, the Contractor will be mud-jacking sections of the curb and gutter in an effort to alleviate major drainage problems. This process involves coring small holes through the curb and gutter section (and driveway apron when necessary) and injecting grout through holes to raise the gutter to the desired grade.

The Contractor will replace areas of broken up pavement as well as a limited amount of curb & gutter. The Contractor will also be replacing some sections of sidewalk that need to be updated to meet new standards for the Americans with Disabilities Act. The projects will take place in several different areas across the city.


Impacts:

Traffic will be maintained during construction, but some lanes may be closed/detoured at times or parking temporarily reduced for work being done. Sidewalks will be closed at times to allow construction to take place.


Contractors:

  • PR-23-E1: Border States Paving
  • PR-23-F1: Border States Paving
  • PR-23-G1: Border States Paving

Timeline:

Construction will begin in May and will continue throughout the season with substantial completion scheduled for the end of September. Not all areas will have construction going on the whole time.


Funding:

This portion of the project will be funded with a combination of Sales Tax Funds and Special Assessments to the benefiting properties, with 50% being funded by Sales Tax Funds and 50% being funded by Special Assessments. Assessed costs are apportioned according to the policy established by the Fargo City Commission.

Fargoparcels.com is a good resource to view the current estimated special assessments for your property. Property owners will receive an estimate for their property. The estimate will change once the project is bid and completed. Special Assessments are payable over 15 years with interest applied.


Purpose:

These projects are needed to correct deficiencies on the streets that have developed over time. Most of the roads in these areas have not had any structural work done to them for 20 years or more. By milling and overlaying the roads at this time, we can extend the life of the road and get a better riding street with improved drainage.