Menu

FargoStreets Hero Image

9th St, 9th Ave,10th Ave, 11th Ave & 12th Ave South Improvements


Zone: SouthWhat zone am I?

Current

Start: Spring 2024

Estimated Completion: Fall 2024

Current Status: (Updated 4/4/2024)

This project is currently scheduled to begin construction April 15, 2024.


Overall Project Map:


9th Street South Overall Map

Overall Project Map


Project Phasing Map


BR-24-B1 Phasing Map

Phasing Map


Project Overview:

Construction activities include the removal and replacement of the existing water main, sanitary sewer, asphalt pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.


Impacts:

This project will be constructed in phases to minimize local impacts as much as possible.


Contractor:

Dakota Underground Inc.


Timeline:

It is anticipated that construction will begin in the spring of 2024 with all roads reopened in the fall of 2024.


Funding:

The project will be funded by a combination of City Funds (Wastewater Utility Funds, Water Utility Funds, Storm Sewer Utility Funds & Infrastructure Sales Tax) and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.


Purpose:

The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.


Public Meeting Video (November 28th, 2023):