9th St, 9th Ave,10th Ave, 11th Ave & 12th Ave South Improvements
Zone: SouthWhat zone am I?
Current
Start: Spring 2024
Estimated Completion: Fall 2024
Current Status: (Updated 9/12/2024)
This project is now substantially complete.
Overall Project Map:
Overall Project Map
Project Phasing Map
Phasing Map
Project Overview:
Construction activities include the removal and replacement of the existing water main, sanitary sewer, asphalt pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.
Impacts:
This project will be constructed in phases to minimize local impacts as much as possible.
Contractor:
Dakota Underground Inc.
Timeline:
It is anticipated that construction will begin in the spring of 2024 with all roads reopened in the fall of 2024.
Funding:
The project will be funded by a combination of City Funds (Wastewater Utility Funds, Water Utility Funds, Storm Sewer Utility Funds & Infrastructure Sales Tax) and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.
Purpose:
The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.