9th St, 8th Ave, 9th Ave, & 10th Ave N Improvements
Zone: NorthWhat zone am I?
Future
Start: Spring 2025
Estimated Completion: Fall 2025
Current Status:
This project is currently scheduled to be bid in late 2024.
Overall Project Map:
Overall Project Map
Project Overview:
Construction activities include the removal and replacement of the existing water main, sanitary sewer, asphalt pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.
Impacts:
This project will be constructed in phases to minimize local impacts as much as possible.
Contractor:
To Be Determined
Timeline:
It is anticipated that construction will begin in the spring of 2025 with all roads reopened in the fall of 2025.
Funding:
The project will be funded with a combination of Sales Tax Funds, Utility Funds (Storm Water, Street Light, Waste Water, Water), and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.
Purpose:
Update the following info as needed with project specific details:
The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.