9th Ave, 10th Ave, 7th St, & 6th St S Improvements


Zone: SouthWhat zone am I?

Future

Start: Spring 2025

Estimated Completion: Fall 2025

Current Status:

This project is currently being designed, and is scheduled to be bid in late 2024.


Overall Project Map:


BR-25-B1_overallmap
BR-25-B1_overallmap

Overall Project Map


Project Overview:

Construction activities include the removal and replacement of the existing water main, sanitary sewer, concrete pavement, asphalt curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.


Impacts:

This project will be constructed in phases to minimize local impacts as much as possible.


Contractor:

To Be Determined


Timeline:

It is anticipated that construction will begin in the summer of 2025 with all roads reopened in the fall of 2025.


Funding:

The project will be funded by a combination of City Funds (Wastewater Utility Funds, Water Utility Funds, Storm Sewer Utility Funds, Traffic/Street Light Utility Funds, & Infrastructure Sales Tax) and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.


Purpose:

The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.