8th St, 10th Ave, & 12th Ave South Improvements
Zone: SouthWhat zone am I?
Future
Start: Spring 2023
Estimated Completion: Fall 2023
Current Status:
This project is currently being bid. Bids will be opened Wednesday, January 18th.
Overall Project Map:

Overall Project Map
Project Overview:
Construction activities include the removal and replacement of the existing water main, sanitary sewer, asphalt pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.
Impacts:
This project will be constructed in phases to minimize local impacts as much as possible.
Contractor:
To Be Determined
Timeline:
It is anticipated that construction will begin in the spring of 2023 with all roads reopened in the fall of 2023.
Funding:
The project will be funded by a combination of City Funds (Wastewater Utility Funds, Water Utility Funds, Storm Sewer Utility Funds & Infrastructure Sales Tax) and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.
Purpose:
The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.