Menu

Fargo Streets

FargoStreets Hero Image

21st Street South Improvements (9th Ave to 13th Ave)


Zone: SouthWhat zone am I?

Completed

Start: Spring 2022

Estimated Completion: Fall 2022

Current Status (Updated 10/3/2022):

This project is substantially complete and fully open to traffic.


Overall Project Map:


BR-22-F1_OverallMap
BR-22-F1_OverallMap

Project Overview:

This project will include the following:

  • New asphalt street
  • New water main, sanitary sewer main, and storm sewer inlets and leads
  • New sidewalks
  • New street lighting

Impacts:

The project will be divided into two phases. This will help reduce how long the street will be closed. Phase 1 will include the work from 13th Avenue to 11th Avenue and Phase 2 will include the work from 11th Avenue to 9th Avenue.


Timeline:

Construction is anticipated to start in May of 2022 and completed by the end of September 2022.


Contractor:

Key Contracting


Funding:

Wastewater Utility Funds, Water Utility Funds, and Special Assessments


Purpose:

This project will install needed infrastructure upgrades and will correct deficiencies on the streets that have appeared over time. The finished product will provide better water and sewer distribution, a better-constructed roadway, improved street lighting and improvements to sidewalks.