1st St N Improvements (32nd Ave to 35th Ave)
Zone: NorthWhat zone am I?
Current
Start: Spring 2024
Estimated Completion: Fall 2024
Current Status (Updated 5/10/24):
This project is currently active, with work scheduled to be completed in the fall of 2024.
Overall Project Map:
Overall Project Map
Project Overview:
Construction activities include the removal and replacement of the existing water main, water and sanitary services, asphalt pavement, concrete curb and gutter, sidewalks, driveway aprons, streetlights, and upgrades to the storm sewer system.
Impacts:
This project will be constructed in phases to minimize local impacts as much as possible.
Contractor:
KPH, Inc.
Timeline:
It is anticipated that construction will begin in the spring of 2024 with all roads reopened in the fall of 2024.
Funding:
The project will be funded by a combination of Prairie Dog Funds and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.
Purpose:
The existing water main is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.