1st Ave S (7th St to 4th St) & Broadway (1/2 Block North of 1st Ave) Improvements
Zone: South, DowntownWhat zone am I?
Future
Start: Summer 2023
Estimated Completion: Fall 2023
Current Status:
This project is currently scheduled to be bid in the spring of 2023.
Overall Project Map:

Overall Project Map
Project Overview:
Construction activities include the removal and replacement of the existing water main, sanitary sewer, concrete pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.
Impacts:
This project will be constructed in phases to minimize local impacts as much as possible.
Contractor:
To Be Determined
Timeline:
It is anticipated that construction will begin in the summer of 2023 with all roads reopened in the fall of 2023.
Funding:
The project will be funded by a combination of Prairie Dog Funds and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.
Purpose:
The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.