Menu

FargoStreets Hero Image

1st Ave S (7th St to 4th St) & Broadway (1/2 Block North of 1st Ave) Improvements


Zone: South, DowntownWhat zone am I?

Future

Start: Summer 2023

Estimated Completion: Summer 2024

Current Status:

Construction is complete for 2023 and will resume in the spring of 2024.


Overall Project Map:


BR-23-J1_OverallMap

Overall Project Map


Phasing Map:


BR-23-J1 Phasing Plan

Phasing Map


Project Overview:

Construction activities include the removal and replacement of the existing water main, sanitary sewer, concrete pavement, concrete curb and gutter, sidewalks, driveway aprons, and upgrades to the storm sewer system.


Impacts:

This project will be constructed in phases to minimize local impacts as much as possible. For full phasing details, please refer to the Phasing Map above.


Contractor:

Dakota Underground Inc.


Timeline:

It is anticipated that construction will begin in the summer of 2023 with all roads reopened in the fall of 2023. Construction will resume in the spring of 2024 and be completed in the summer of 2024.


Funding:

The project will be funded by a combination of Prairie Dog Funds and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.


Purpose:

The existing water main and sanitary sewer is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.


Public Meeting Video (May 15, 2023):