Lilac Lane North Improvements


Zone: NorthWhat zone am I?

Future

Start: Spring 2025

Estimated Completion: Fall 2025

Current Status:

This project is currently scheduled to be bid in late 2024.


Overall Project Map:


BR-25-C1_OverallMap

Overall Project Map


Project Overview:

Construction activities include the removal and replacement of the existing water main and services, sanitary services, asphalt pavement, curb and gutter, sidewalks, driveway aprons, street lights, and upgrades to the storm sewer system.


Impacts:

This project will be constructed in phases to minimize local impacts as much as possible.


Contractor:

To Be Determined


Timeline:

It is anticipated that construction will begin in the spring of 2025 with all roads reopened in the fall of 2025.


Funding:

The project will be funded by a combination of City Funds (Wastewater Utility Funds, Water Utility Funds, Storm Sewer Utility Funds, Street Light Utility Funds & Infrastructure Sales Tax) and Special Assessments to the benefiting properties. Special Assessments will be applied per City policy.


Purpose:

The existing water main is being replaced to minimize impacts and costs associated with breaks/failures. The street reconstruction is necessary because the existing street section has deteriorated significantly and has exceeded its life expectancy.


Public Meeting Video (Date, 2024):

Public Meeting video will be added below via Video Embed once the meeting takes place.