Mill & Overlay Project 2017


Zone: North, SouthWhat zone am I?

Completed

Start: May 2017

Estimated Completion: Fall 2017

Project Overview:

This project is part of the city’s annual infrastructure improvement efforts and impacts multiple areas of Fargo each construction season. Milling and overlaying existing pavement corrects surface deficiencies that have developed over time, in order to provide a better riding street section with improved drainage. It is a preventative maintenance project that serves as a cost effective way to extend the life of pavement, saving the city and its residents time, money and resources.

Impacts:

Traffic will be maintained during construction, but some lanes may be closed at times or parking temporarily reduced for work being done. This work will be performed on streets and avenues in various areas of the city. Most of this year’s work is contained to the area bounded by I-94, University Drive, 32nd Avenue S and 25th Street. There is also a small portion between 10th Street N, 36th Avenue N and Royal Oaks Drive N, and along 15th Avenue S between 42nd Street to 45th Street.

The specific areas include:

Section 1: Current work

  • Royal Oaks Drive N north of 37th Avenue N
  • 36th Avenue N from 10th Street N to University Drive N
  • 10th Street N from 37th Avenue N to 40th Avenue N

Section 2:

  • 22nd Avenue S from 15th Street S to 16th Street S
  • 23rd Avenue S from 18th Street S to 25th Street S
  • 24th Avenue S from 15th Street S to 16th Street S
  • 24th Avenue S from 22nd Street S to 25th Street S
  • 25th Avenue S from 18th Street S to 25th Street S
  • 25 ½ Avenue S from 18th Street S to 25th Street S
  • 26th Avenue S from 18th Street S to 25th Street S
  • 26 ½ Court S from 18th Street S to 26 ½ Avenue S
  • 26 ½ Avenue S from 18th Street S to 25th Street S
  • 28th Avenue S from 15th Street S to 23rd Street S
  • 28 ½ Avenue S from 15th Street S to 17th Street S
  • 29th Avenue S from 15th Street S to 23rd Street S
  • 30th Avenue S from University Drive S to 25th Street S
  • 30 ½ Avenue S from 22nd Street S to 25th Street S
  • 31st Avenue S from 15th Street S to 22nd Street S
  • 15th Street S from 21st Avenue S to 25th Avenue S
  • 15th Street S from 27th Avenue S to 32nd Avenue S
  • 16th Street S from 21st Avenue S to 25th Avenue S
  • 17th Street S from 28th Avenue S to 32nd Avenue S
  • Cul-de-sac north of 18th Street S
  • 18th Street S from 25th Avenue S to 32nd Avenue S
  • 19th Street S from 30th Avenue S to 31st Avenue S
  • 20th Street S from 30th Avenue S to 31st Avenue S
  • 21st Street S from 30th Avenue S to 31st Avenue S
  • 22nd Street S from 18th Street S to 32nd Avenue S
  • 23rd Street S from 28th Avenue S to 32nd Avenue S
  • Arrowhead Road S from 25th Avenue S to 27th Avenue S
  • American Way S from Arrowhead Road S to west of Pacific Drive S
  • Atlantic Drive S from American Way S to 27th Avenue S
  • Pacific Drive S from American Way S to 27th Avenue S
  • Viking Circle S
  • Columbus Circle S

Timeline:

Construction began this spring and will continue throughout the season, when contractors can fit work into their schedules with other projects. All mill and overlay improvements should be complete by fall.

Project contractors are currently working on Section 1 and expect to get all concrete work done in this area in the next two weeks.

Purpose:

The above named streets and avenues are in need of rehabilitation. A mill and overlay will provide a new wearing surface as well as correct deficiencies which have appeared over time. The project also improves drainage and safety in the area. Rehabilitation results in long-term cost savings for Fargo and its residents.

Funding:

The estimated cost for this year’s work is $3.6 million. Half of this project is funded by the city and half is assessed to the adjacent properties.