4th Avenue N: Reconstruction & Water Main Replacement


Zone: DowntownWhat zone am I?

Current Project

Project Start: July 2017

Estimated Completion: Fall 2017

Current Project Map

Current Project Map


4th Avenue N Project Overview Map

4th Avenue N Project Overview Map


Project Overview:

This project will include complete roadway reconstruction, water main replacement, sanitary and storm sewer replacement, new street lighting and sidewalks. This stretch of 4th Ave. N, as well as many underground utilities in the area, were installed more than 100 years ago. The road is deteriorating and utilities are breaking, so replacement will minimize impacts and costs.

Impacts:

4th Ave. N will be done in two phases. Phase one of the project will consist of work on 3rd St. N. Crews have approximately three weeks to complete work on 3rd St. N, then will progress through the project working east to west.

Phase two of the project will impact 4th Ave. N from 4th St. N to east of Broadway. Project work for phases one and two will overlap so crews can complete the project on time, closing 4th Ave. N from east of Broadway through the 3rd St. N intersection.

Sidewalks will be maintained for pedestrians and business access during both phases.

There will not be any posted detour routes, but drivers should use side streets to get around the work zone.

Timeline:

Construction efforts began July 13th. All work should be completed by late fall.