25th Street and 13th Avenue South Intersection Project Starts on Median Removals Thursday

09/13/2017

Zone: South
Project: 25th Street & 13th Ave S Intersection Reconstruction

Beginning the evening of Wednesday, September 13, crews will begin to set-up the traffic control for the roadway rehabilitation and reconstruction project at the intersection of 25th Street and 13th Avenue South.

Starting Thursday morning, motorists will drive through an active work zone and crews will begin roadway removals in the median areas surrounding the intersection. Project work on the intersection rehabilitation will continue into November.

Throughout the intersection, for drivers in all directions:

  • One driving lane with left-hand turning lanes will be open – motorists will shift to the outside driving lane on their respective side during removals
  • Median lane will be closed to traffic

Once removals are complete in the median area, crews will asphalt this area to allow for shifting traffic lanes during each phase of the project.

The intersection will not fully close to traffic, however at times certain traffic movements will be limited to right-in and right-out in the zone to help with traffic flow out of business driveways in the intersection.

After the median removals are complete, crews will begin work on the second phase and begin removing the first intersection corner (northwest quadrant by Wells Fargo), one lane of traffic with turning lanes in each direction will be maintained through the work zone. This project work is anticipated to start in one week and then will be clockwise to each corner of the intersection.

One sidewalk crossing for east/west and north/south will be maintained. At times stretches will be closed to accommodate the work occurring in the corner.

**Please remember all schedules are tentative and weather dependent.

Speeds are reduced in the work zone so drivers are reminded to slow down, eliminate distractions and pay attention to signage, as crews may be working near traffic.

The concrete pavement repair project (phase 4) on 25th Street S from the intersection to 17th Avenue S will be complete by spring 2018.