Street Light Improvement Projects: 2017


Zone: North, South, DowntownWhat zone am I?

Completed

Start: May 2017

Estimated Completion: December 2017

Project Overview:

The City of Fargo will be installing new street lights to improve infrastructure and safety in specific areas of the city. These locations either do not have any lighting, or have inadequate lighting. The following locations will receive improvements this season:

  • Oak Grove Area: BNSF Railway to 12th Ave. N, Broadway N to Oak Grove Park
  • 25th Ave. N to 30th Ave. N from 10th St. to Elm St.
  • South High Area: 13th Ave. S to I-94, University Dr. to 21st St. S
  • 7th St N & 8th St. N, 15th Ave. to 17th Ave.

Current Status:

Construction has not started for this season.

Timeline:

Work will begin in the spring of 2017. Select neighborhoods were improved in summer/fall 2016.